砂・砂利上へのセラミックストーン舗装材施工

必要材料・層構成・スラブ5工程・Pavè工程・排水・目地確認に沿って砂または砂利上に施工します。
LuCharlotte LuCharlotte 8 分以内に読めます 更新済み

Approved sintered stone slabs can be dry-laid on a prepared sand or gravel bed without adhesive. Build and compact the support layers, maintain the drainage fall, place the slabs with the specified spacers, level them with a rubber mallet, restrain the edges and finish the joints with a material compatible with the selected system.

Dry laying makes suitable slabs removable and reusable because they are not bonded to the bedding layer. The illustrated method uses a minimum 2% drainage fall. Layer depths, joint widths, traffic limits and the choice of sand, gravel, polymeric sand or grout still come from the exact paver detail and the project conditions.

“No adhesive” applies to the dry-laid slab route shown here. The separate Pavè block detail below includes a reinforced screed and may use binder or cementitious joint material where its specification requires it.

Prepare the materials and tools before you start

Place every material and control tool on site before screeding the bedding layer. Check that the slab or Pavè format is approved for the intended detail, and keep the plate compactor for the soil, sub-base and bedding—not the finished slab surface.

Sintered stone slab for dry laying on sand or gravel

Sintered stone slabs

Inspect the approved size, finish, thickness, edges and batch before the bedding layer is disturbed.

Sintered stone Pavè block for installation on a prepared bedding layer

Sintered stone Pavè

Use the Pavè sequence only for the block format and base construction shown in its approved detail.

Cross spacer used to keep joints aligned between paver slabs

Cross spacers

Keep the planned joints open and aligned; use the spacer size stated by the selected slab system.

Plate compactor for preparing paver soil and aggregate layers

Plate compactor

Compact the ground, sub-base and bedding in controlled lifts before the pavers are placed.

Rubber mallet for seating and levelling sintered stone pavers

Rubber mallet

Seat each unit with controlled taps; never strike exposed corners or use the mallet to hide an unstable bed.

Spirit level for checking paver plane and drainage fall

Level and datum lines

Set finished elevation and the drainage fall before placement, then check the plane as each row advances.

Bagged bedding or joint material for a paver installation system

Bedding and joint materials

Confirm the specified sand, pea gravel, binder, polymeric sand or compatible grout before opening bags.

Clean bucket for mixing or cleaning during paver installation

Clean buckets

Separate mixing, clean-water and residue-removal buckets so joint materials are not contaminated.

Read the layer build-up before you excavate

The correct excavation follows the complete section, not the thickness of the visible paver. The main diagram above shows a ground installation; the next diagrams show a terrace or roof build-up and a Pavè ground build-up.

Slab build-up on the ground

For the illustrated ground detail, the layers are: A) slab with cross spacer, B) sand or gravel, C) non-woven fabric, D) drainage layer and E) soil. Compact the supporting ground and preserve the drainage path through every layer.

A — Slab with cross spacer

B — Sand or gravel

C — Non-woven fabric

D — Drainage layer

E — Soil

Slab build-up on a terrace or roof

The sand or gravel ballast sits above the separation, insulation, moisture-control, waterproofing and sloped structural layers. Do not place ballast until waterproofing, outlets and finished elevations have been approved.

Terrace or roof build-up for sintered stone slabs laid on sand or gravel
Illustrated terrace or roof dry-lay build-up. The letters identify each functional layer; the project designer controls actual products, thicknesses and interfaces.

A — Slab with cross spacer

B — Sand or gravel ballast layer

C — Separation layer

D — Thermal insulation

E — Moisture-control layer

F — Waterproofing layer

G — Sloped screed

H — Structural floor

Pavè build-up on the ground

The Pavè detail is a different assembly: the blocks sit on sand or gravel above a reinforced screed, sub-base and soil. Treat its bonded or cementitious elements as part of the Pavè specification, not as proof that slab dry laying needs adhesive.

Ground build-up for sintered stone Pavè blocks over sand or gravel and reinforced screed
Illustrated Pavè ground build-up with the visible paving, bedding, reinforced screed, sub-base and soil.

A — Pavè blocks

B — Sand or gravel

C — Reinforced screed

D — Sub-base

E — Soil

Depth note: the supplied slab method shows a 10–30 cm (4–12 in) sand or gravel layer over a non-woven or separation layer. This is the illustrated system's range, not a universal Funtek depth. Soil strength, frost, rainfall, paver format, edging and traffic can require another engineered section.

How to dry-lay sintered stone slabs on sand or gravel

Complete the slab installation in five controlled stages. Keep at least a 2% fall in the illustrated method, avoid walking on freshly screeded bedding and check each slab for rocking before moving to the next row.

Step 1 spreading and screeding a sand or gravel bedding layer
1

Spread and screed the bedding layer

Place the specified sand or gravel over the non-woven fabric or separation layer, establish the finished elevation and screed it evenly. Add binder only when the approved system calls for it.

Step 2 compacting the paver soil, base or bedding before slab placement
2

Compact the supporting layers

Use the plate compactor on the soil, drainage layer, sub-base or bedding as the selected detail specifies. Restore the planned plane and a minimum 2% drainage fall after compaction.

Step 3 placing sintered stone slabs with cross spacers
3

Place the slabs with cross spacers

Lower each slab onto undisturbed bedding instead of dragging it into position. Insert the specified cross spacers and check the grid, perimeter clearance and edge restraint as work advances.

Step 4 levelling a sintered stone slab with a rubber mallet
4

Seat and level each slab

Tap the slab with a rubber mallet while checking the plane and drainage direction. Lift and correct the bedding if the unit rocks; do not force an unsupported slab flat.

Step 5 filling and cleaning joints between dry-laid sintered stone slabs
5

Fill and clean the joints

Use the approved joint material for the bedding and drainage concept. Sweep or apply it to the required depth, clean residue before it hardens and keep outlets open.

Do not run a vibrating plate compactor over installed sintered stone slabs unless the exact paver system expressly permits a protected procedure. Compact the support layers first; seat the slabs with a rubber mallet.

How to lay sintered stone Pavè blocks

The Pavè sequence uses a reinforced screed and a thinner compacted bedding layer. Let the screed cure, preserve the drainage plane and use the joint width and fill specified for the block system.

Pavè step 1 constructing a reinforced screed above the sub-base
1

Construct and cure the reinforced screed

Form a reinforced screed about 5 cm (2 in) thick over the prepared sub-base, following the selected detail for reinforcement, fall and curing. Do not cover it before it has reached the required condition.

Pavè step 2 screeding a sand or pea gravel bedding layer
2

Place at least 2 cm of bedding

Spread a sand or pea-gravel mixture at least 2 cm (0.8 in) thick over the cured screed. Screed the layer evenly without blocking the planned drainage direction.

Pavè step 3 compacting the sand or pea gravel bedding layer
3

Compact the bedding layer

Compact the sand or pea gravel with suitable equipment before laying the blocks. Recheck the finished elevation and fall, then avoid disturbing the prepared surface.

Pavè step 4 laying and seating blocks with a rubber mallet
4

Lay and seat the Pavè blocks

Place the blocks in the planned pattern and maintain 5–20 mm joints where this illustrated system applies. That equals about 0.2–0.8 in. Seat each block with a rubber mallet and keep the rows aligned.

Pavè step 5 filling the joints after block installation
5

Fill the joints and clean the surface

Fill the joints with the compatible polymeric sand or cementitious grout named by the system. Remove residue promptly, protect the work for the required curing period and keep drainage outlets clear.

Check the installation before use

The finished field is ready only when the pavers are stable, joints are consistent and water reaches the intended outlet. Inspect the surface before furniture, landscaping or final cleaning hides the evidence.

Check Pass condition If it fails
Stability No slab or block rocks under normal foot pressure Lift it, correct the bedding and reseat it before joint filling
Drainage The planned fall continues to a working outlet without ponding Trace the high or blocked area and correct the plane or outlet
Joints Widths remain consistent and the fill reaches the specified depth Reset drifting units and refill only after the grid is stable
Edges Perimeters and cut pieces are supported and restrained Rebuild weak edges; joint fill cannot replace edge restraint
Surface No chipped units, cement haze or loose joint residue remain Replace damage and use only the approved cleaning method

Fix common sand or gravel installation mistakes

  • A slab rocks after placement: lift it and rebuild the bedding beneath it. Do not lock movement in with grout.
  • Water ponds between rows: stop placement and restore the planned fall before more pavers hide the problem.
  • Joints close at one edge: reset the row with the correct spacers and verify perimeter clearance.
  • The edge course moves: install or correct the designed restraint; joint material alone does not hold the field in place.
  • A cut chips or cracks: replace it and correct the blade, feed and support method. For cutting and dust-control planning, use the complete sintered stone installation guide.

The Bottom Line

Sintered stone slabs approved for dry laying can be installed on a prepared sand or gravel bed without adhesive. The result depends on a compact, draining and restrained base, controlled spacing, careful mallet levelling and a compatible joint finish. Use the separate Pavè sequence only when its reinforced screed and block detail match the project.

Plan Your Sintered Stone Paver Project

Send the site type, area, slab or Pavè format, soil or structural base, drainage plan and preferred joint finish. Funtek can review the material and project-supply brief before installation begins.

筆者について

LuCharlotte

焼結石(Sintered Stone)専門メーカー兼テクニカルアドバイザー

LinkedInでつながる

LuCharlotteは、焼結石(Sintered Stone)の製造実務、素材試験、案件仕様の視点から執筆しています。建築士・デザイナー・加工業者・プロジェクトの購買担当者様向けに、表面性能、スラブ規格、加工の考え方、仕上げ選び、用途適性など、現場で役立つ内容をわかりやすくお届けしています。素材選びにおける技術的な判断を、より明確で正確、そして検証しやすいものにすることが、彼女の目的です。

セラミックストーン舗装材施工 FAQ

01

セラミックストーン舗装材は砂や砂利の上に施工できる?

正確なスラブ/舗装材が乾式システムに承認されている場合は可能です。指定の締固め支持層・敷床層上へ、有効な排水、端部拘束、管理目地、必要スペーサーとともに施工し、緩い土へ直接置かないでください。

02

乾式施工のセラミックストーン舗装材に接着剤は必要?

ここに示す乾式スラブ工法では、スラブと砂/砂利敷床の間に接着剤を使いません。結合材は選定システムで指定する場合のみ加え、別のPavèブロック詳細には補強スクリード/セメント系目地材が含まれる場合があります。

03

砂・砂利上の舗装材に必要な勾配は?

図示方法では、所定の排水口へ水を流すため最低2%勾配を採用します。最終勾配はプロジェクトの排水設計、敷居、アクセシビリティ、防水、地域規則に照らして確認してください。

04

施工済みセラミックストーン舗装材の上でプレートコンパクターを使える?

スラブ設置前に土、路盤、敷床層へプレートコンパクターを使います。正確なメーカー・システムが保護面締固め手順を明示許可しない限り、施工済みスラブ上で運転せず、ゴムハンマーで据え付けてください。

05

舗装材の目地には何を充填する?

選定舗装材、敷床、排水システムに承認された目地材を使います。詳細により清浄砂、ポリマー砂、適合セメント系グラウトなどです。指定目地形状、清掃、養生指示に従ってください。